DCMA 14-point check with AI in Primavera P6

Run the DCMA 14-point assessment on a P6 project from Claude, Cursor, VS Code or any MCP client, with the thresholds your project already has in P6, then drill into the activities behind each failed check.

Tools: p6_health_check, p6_health_check_compare, p6_cpm_validate · Profile: Basic is enough for the check, Full for the comparison

The 14 checks

The DCMA 14-point assessment screens a schedule for the defects that make its dates unreliable: missing logic, leads and lags, constraints, float and duration outliers, dates that make no sense, progress against the baseline. The server computes every check on the open activities of the last P6 schedule run (F9), with level of effort and WBS summary activities left out, as the DCMA guidance intends.

DCMA default thresholds. High float and high duration use 44 working days of each activity's calendar.
CheckWhat it countsDefault threshold
1. LogicOpen activities without a predecessor or a successorat most 5 %
2. LeadsLinks with a negative lag0 %
3. LagsLinks with a positive lagat most 5 %
4. Relationship typesFinish-to-start share of the linksat least 90 %
5. Hard constraintsMandatory and other hard constraintsat most 5 %
6. High floatTotal float over 44 working daysat most 5 %
7. Negative floatTotal float below zero0 %
8. High durationRemaining duration over 44 working daysat most 5 %
9. Invalid datesForecast dates before, or actual dates after, the data date0 %
10. ResourcesActivities with duration and no resourcereport only
11. Missed tasksBaseline activities due by the data date and not finished on timeat most 5 %
12. Critical path testDoes a delay on the critical path move the finish as much?pass
13. CPLICritical path length indexat least 0.95
14. BEIBaseline execution indexat least 0.95

Before you start

  • Install the server and select your P6 database in its Settings window (install steps), or load XER files in XER-only mode.
  • Press F9 in P6 first: the check reads the dates and float of the last schedule run. Reading does not need P6 to be closed.
  • Missed tasks and BEI need a baseline. The server takes the project baseline set in P6, or the one you name.

Run the check

Run a DCMA 14-point health check on DEMO-SS225 and explain each failed check in one line.

The assistant calls p6_health_check(project="DEMO-SS225"). The server returns, per check, the count, the denominator, the percentage, the threshold, pass or fail and a sample of 15 activities or links, plus a score and a weighted grade. On the demo project at its data date of 26 October 2026:

DEMO-SS225, synthetic data, DCMA default thresholds (the project has none set in P6).
CheckResultThresholdStatus
Logic0 of 75 (0 %)at most 5 %Pass
Leads0 of 1450 %Pass
Lags15 of 145 (10.3 %)at most 5 %Fail
Relationship types (FS)130 of 145 (89.7 %)at least 90 %Fail
Hard constraints0 of 75at most 5 %Pass
High float28 of 75 (37.3 %)at most 5 %Fail
Negative float37 of 75 (49.3 %)0 %Fail
High duration2 of 67 (3.0 %)at most 5 %Pass
Invalid dates0 of 2140 %Pass
Resources13 of 67 (19.4 %)report onlyInfo
Missed tasks134 of 149 (89.9 %)at most 5 %Fail
Critical path testfinish movespassPass
CPLI0.85at least 0.95Fail
BEI0.93at least 0.95Fail

Score: 6 checks passed and 7 failed of the 13 evaluated (46.2 %); weighted score 70.5 points, grade C. The weighted score also counts logic density (links per open activity, here 1.93 against a minimum of 1.5), which is outside the DCMA 14 and outside the score.

A useful reading of this result: negative float on half of the open work and a CPLI of 0.85 say the same thing, the forecast finish is beyond the must finish by date; the many missed tasks say it did not happen suddenly. The lags and the non-FS links are the first logic questions to ask the scheduler.

Drill into a failed check

Each check can be paged in full, in the same snapshot, with the activities or links behind it.

Which open activities fail the high float check on DEMO-SS225? List them as Activity ID - name with their total float, largest first.

The assistant calls p6_health_check(project="DEMO-SS225", check="high_float") and pages the 28 activities. The same works for lags, fs_links, negative_float, missed_tasks and the other checks. For the logic check, ask for the dangling ends too: p6_dangling lists open starts and open finishes and suggests the link that would close each one.

Why the critical path test can say "not evaluated"

The test delays the most critical open activity by 100 working days in the server's CPM engine and checks that the finish moves as much. It runs only when that engine reproduces P6's own dates on the project. Ask "validate the CPM engine on DEMO-SS225" to see the match rate from p6_cpm_validate.

Use your own thresholds

P6 Professional stores schedule check settings per project. When they exist, the server uses them instead of the DCMA defaults, including the checks you turned off, and says so in threshold_source. You can also override a threshold for one run:

Run the health check on DEMO-SS225 with a lags threshold of 10 % and high float above 30 days.

That becomes thresholds={"lags": 10} and high_float_days=30. Nothing is stored: the next run is back to the project's settings.

Follow the trend

Every full run saves a snapshot next to the server's logs. After the next update, ask:

Compare today's DCMA check of DEMO-SS225 with the previous one. Which checks got worse, and which activities are new in them?

p6_health_check_compare compares the totals, every check value and the activities or links that entered or left each check. When the CPM engine version changed between two runs, it says so.

What the check does not tell you

  • A schedule can pass all 14 checks and still be wrong: durations, sequence and resource assumptions need a planner's review.
  • Thresholds are screening values, not contract requirements, unless your contract says so.
  • The check reads the last F9. If someone edited the project since, the result says the schedule is stale.